A Construction Hazard Identification (HAZID) study for an oil and gas project follows a structured format to systematically identify potential hazards, assess their risks, and propose mitigation measures before construction begins.

Here is a standard format for a Construction HAZID.


 

1. Introduction and Objectives

 

This initial section sets the stage for the HAZID review.

  • Project Overview: A brief description of the oil and gas project, including its location, scope, and key construction phases (e.g., site preparation, civil works, structural erection, mechanical installation, electrical and instrumentation).

  • HAZID Scope: Clearly defines the physical boundaries, project timeline, and specific construction activities covered by the HAZID study. It also lists what is excluded.

  • Objectives: The primary goals of the study.

    • To systematically identify hazards associated with construction activities.

    • To analyze the causes and potential consequences of these hazards.

    • To evaluate existing safeguards and controls.

    • To propose additional recommendations to reduce risks to an acceptable level (As Low As Reasonably Practicable – ALARP).

    • To assign responsibility for implementing the recommendations.


 

2. Methodology

 

This section details the “how” of the HAZID process.

  • HAZID Team: Lists the participants, including their roles and affiliations (e.g., Facilitator, Scribe, Project Manager, Construction Lead, Safety Engineer, discipline engineers like Civil, Mechanical, Electrical).

  • Technique: Explains the method used, which is typically a structured brainstorming session guided by a set of “guidewords” applied to different project areas or activities.

  • Guidewords: A list of prompts used to stimulate discussion. Common construction guidewords include:

    • Excavation / Trenching

    • Lifting / Rigging

    • Work at Height

    • Hot Work (Welding, Grinding)

    • Confined Space Entry

    • Hazardous Materials (Handling/Storage)

    • Pressure Testing (Hydrostatic/Pneumatic)

    • Simultaneous Operations (SIMOPS)

    • Vehicle / Mobile Equipment Movement

    • Dropped Objects

  • Risk Assessment Matrix: The tool used to rank risks. It’s typically a 5×5 matrix that combines Severity (from catastrophic to negligible) with Likelihood (from frequent to rare) to produce a risk level (e.g., Low, Medium, High, Critical).

 

Example Risk Matrix

 

Severity 1 (Slight)2 (Minor)3 (Moderate)4 (Major)5 (Catastrophic)
A (Frequent)MediumHighHighCriticalCritical
B (Likely)MediumMediumHighHighCritical
C (Occasional)LowMediumMediumHighHigh
D (Unlikely)LowLowMediumMediumHigh
E (Rare)LowLowLowMediumMedium

 

3. HAZID Worksheet (Hazard Register)

 

This is the core output of the HAZID session, typically documented in a spreadsheet. It records the discussion for each identified hazard.

IDGuide Word / ActivityHazardPotential ConsequencesCausesExisting SafeguardsRisk Ranking (S, L, R)RecommendationsAction PartyDue Date
1Lifting OperationsDropped Load– Fatalities/Injuries
– Equipment Damage
– Project Delay
– Rigging failure
– Crane malfunction
– Human error
– High winds
– Certified lifting gear
– Competent operators/riggers
– Lift plan & permit
– Barricading of lift area
S: 5
L: D
R: High
1.1 Develop a critical lift plan for all lifts > 10 tons.
1.2 Ensure 3rd party inspection of all cranes prior to mobilization.
Construction Manager[Date]
2ExcavationTrench Collapse– Buried personnel
– Asphyxiation
– Damage to underground services
– Unstable soil
– No shoring/benching
– Heavy equipment near edge
– Soil analysis
– Permit to Work system
– Daily trench inspection
S: 5
L: C
R: High
2.1 Mandate shoring or sloping for all excavations deeper than 1.2m.
2.2 Use cable locators to scan all areas before digging.
HSE Lead / Civil Lead[Date]

Column Explanations:

  • ID: A unique number for tracking.

  • Hazard: What could cause harm (e.g., dropped object, toxic gas release).

  • Consequences: The outcome if the hazard is realized (e.g., injury, asset damage).

  • Causes: The triggers that could lead to the hazard.

  • Existing Safeguards: Controls already planned or in place (e.g., procedures, PPE, design features).

  • Risk Ranking: The assessment of Severity (S), Likelihood (L), and resulting Risk (R) with existing safeguards in place.

  • Recommendations: Specific, actionable steps to further reduce the risk.

  • Action Party: The person or department responsible for implementing the recommendation.


 

4. Reporting and Close-Out

 

The final stage involves documenting and acting on the findings.

  • Executive Summary: A high-level overview of the key findings, critical risks identified, and a summary of high-priority recommendations.

  • List of Recommendations: A consolidated list of all recommendations generated during the HAZID, often prioritized by risk level.

  • Action Tracking Register: The HAZID worksheet itself becomes a live document used to track the implementation and close-out of each recommendation. This is crucial for ensuring the value of the study is realized.

  • Appendices: May include drawings reviewed, team attendance sheets, and the full risk matrix definitions.

Leave a Reply

Your email address will not be published. Required fields are marked *