Phase 1 — Hazard & Risk Assessment (IEC 61511)
Verification Checklist
| # | IEC 61511 Clause | Requirement | Outcome | Verification Comments | Recommendation | By | Status |
|---|---|---|---|---|---|---|---|
| 1 | 8.2 | Confirm process hazards are identified and documented. | |||||
| 2 | 8.2.1 | Verify recognized methodology used (e.g., HAZOP, What-If, Checklist). | |||||
| 3 | 8.2.2 | Check inclusion of start-up, shutdown, and abnormal conditions. | |||||
| 4 | 8.2.3 | Ensure initiating events and consequences are quantified/qualified. | |||||
| 5 | 8.2.4 | Review risk matrix alignment with corporate tolerability (ALARP) criteria. | |||||
| 6 | 8.2.5 | Verify protective layers identified and effectiveness justified (IPLs). | |||||
| 7 | 8.2.6 | Confirm frequency/severity data sources are credible and traceable. | |||||
| 8 | 8.2.7 | Ensure team competence evidence (CVs/training/experience) is recorded. | |||||
| 9 | 8.2.8 | Confirm all study assumptions are explicitly documented. | |||||
| 10 | 8.2.9 | Validate that the study was independently facilitated or reviewed. | |||||
| 11 | 8.2.10 | Ensure environmental, asset, and personnel impacts considered. | |||||
| 12 | 8.2.11 | Verify recommendations/actions are tracked to closure with owners/dates. | |||||
| 13 | 8.2.12 | Confirm interface with corporate/site risk register is maintained. | |||||
| 14 | 8.2.13 | Validate data consistency across all HAZOP nodes/sections. | |||||
| 15 | 8.2.14 | Check safeguards match latest P&IDs, cause-&-effect and narratives. | |||||
| 16 | 8.2.15 | Verify assumptions/initiators are carried forward for LOPA/SIL studies. | |||||
| 17 | 8.2.16 | Confirm extreme operating/abnormal scenarios were reviewed (e.g., utilities loss). | |||||
| 18 | 8.2.17 | Validate correct consequence categories and definitions were applied. | |||||
| 19 | 8.2.18 | Verify lessons learned / incident data were considered in the study. | |||||
| 20 | 8.2.19 | Ensure the final H&RA/HAZOP report is approved and signed by stakeholders. | |||||
| 21 | 8.2.20 | Cross-check tag references against the latest approved P&IDs and lists. | |||||
| 22 | 8.2.21 | Confirm recommendations transferred to the project action tracker (with due dates). | |||||
| 23 | 8.2.22 | Verify study minutes, worksheets, and attendance records are archived. | |||||
| 24 | 8.2.23 | Check the formal link from HAZOP to subsequent SIL/LOPA activities is established. | |||||
| 25 | 8.2.24 | Confirm re-validation / re-study frequency is defined and scheduled. |
Note: Clause numbers follow IEC 61511 Part 1, Clause 8.2 (Hazard and Risk Assessment) and common sub-items used in practice.
Phase 2 — Allocation of Safety Functions to Protection Layers (IEC 61511)
Verification Checklist
| # | IEC 61511 Clause | Requirement | Outcome | Verification Comments | Recommendation | By | Status |
|---|---|---|---|---|---|---|---|
| 1 | 9.2 | Verify all independent protection layers (IPLs) identified and credited correctly. | |||||
| 2 | 9.3 | Check functional and physical independence between IPLs (including SIS vs BPCS). | |||||
| 3 | 9.4 | Validate PFD/PFH calculations and risk reduction factors for each IPL/SIF. | |||||
| 4 | 9.5 | Confirm that target SIL for each SIF is properly derived from risk gap/LOPA results. | |||||
| 5 | 9.6 | Ensure overall risk is within company tolerability criteria (ALARP demonstration). | |||||
| 6 | 9.7 | Verify assumptions used in LOPA are documented, justified, and traceable to sources. | |||||
| 7 | 9.8 | Confirm enabling conditions, conditional modifiers, and dependencies are accounted for. | |||||
| 8 | 9.9 | Review LOPA worksheet completeness and accuracy (initiators, IPL credits, consequences). | |||||
| 9 | 9.10 | Ensure process demand rates and frequencies are realistic and referenced to data/experience. | |||||
| 10 | 9.11 | Validate credit assigned to alarms and operator response (time to respond vs process safety time). | |||||
| 11 | 9.12 | Confirm BPCS protection claims are justified and do not violate independence requirements. | |||||
| 12 | 9.13 | Check physical separation, segregation, and common cause protection between IPLs/SIFs. | |||||
| 13 | 9.14 | Verify SIFs with similar causes are rationalized (no double counting of protection credits). | |||||
| 14 | 9.15 | Confirm external events and site-wide hazards considered in allocation (utilities, power loss). | |||||
| 15 | 9.16 | Verify interaction between high-integrity pressure protection (HIPS) and relief (PSV) is addressed. | |||||
| 16 | 9.17 | Ensure documentation traceability from HAZOP/LOPA to SIF list and SRS (unique IDs maintained). | |||||
| 17 | 9.18 | Confirm multidisciplinary review by process, safety, and I&C specialists completed. | |||||
| 18 | 9.19 | Check correctness of units, frequencies, and calculation methods (peer review performed). | |||||
| 19 | 9.20 | Validate SIL determination against corporate templates/tools and IEC methods. | |||||
| 20 | 9.21 | Ensure final LOPA/Allocation report is approved, signed, and baselined in document control. | |||||
| 21 | 9.22 | Verify all allocation assumptions/requirements are transferred into the SRS for each SIF. | |||||
| 22 | 9.23 | Check interface with mechanical relief design; avoid conflicting protection philosophies. | |||||
| 23 | 9.24 | Confirm LOPA/Allocation action items are logged with owners and due dates, tracked to close. | |||||
| 24 | 9.25 | Validate re-assessment interval defined (e.g., at major changes or set periodicity). | |||||
| 25 | 9.26 | Ensure version control on worksheets/models; archive superseded versions with rationale. |
Note: Clause numbers follow IEC 61511 Part 1, Clause 9 (Allocation of safety functions to protection layers) and typical sub-items used in practice.
Phase 3 — Safety Requirements Specification (SRS) (IEC 61511)
Verification Checklist
| # | IEC 61511 Clause | Requirement | Outcome | Verification Comments | Recommendation | By | Status |
|---|---|---|---|---|---|---|---|
| 1 | 10 | All SIFs captured from LOPA/Allocation with unique IDs and titles. | |||||
| 2 | 10 | Functional requirements defined: process variable, trip setpoint, action, final element(s). | |||||
| 3 | 10 | Safety integrity requirements stated: target SIL, PFDavg/PFH, risk reduction factor, architectural constraints. | |||||
| 4 | 10 | Process Safety Time (PST) determined and referenced; response time budget allocated per SIF path. | |||||
| 5 | 10 | Mode of operation identified (low demand / high demand / continuous) and justified for each SIF. | |||||
| 6 | 10 | Proof test interval, proof test coverage, and test procedures specified at SIF and device level. | |||||
| 7 | 10 | Diagnostic coverage, fault detection, and fault reaction (safe state) requirements defined. | |||||
| 8 | 10 | Trip reset, restart, inhibit/override, and bypass philosophy defined with authorization levels and limits. | |||||
| 9 | 10 | Interface requirements to BPCS, F&G, electrical, and packages documented (signals, protocols, isolation). | |||||
| 10 | 10 | Environmental, EMC, electrical, and mechanical conditions defined (temperature, IP rating, vibration, area class). | |||||
| 11 | 10 | Redundancy and voting logic (sensor/logic/final elements) specified; common-cause mitigation addressed. | |||||
| 12 | 10 | Setpoint calculation, drift limits, and trip accuracy/tolerance requirements defined and justified. | |||||
| 13 | 10 | Human–Machine Interface (HMI) and alarm/event requirements specified (messages, priorities, colors, timestamps). | |||||
| 14 | 10 | Power supply philosophy (UPS, redundancy, brownout/blackout behavior) defined for each SIF path/device. | |||||
| 15 | 10 | Maintenance access and test provisions (test ports, simulation points, PST enablers) defined in SRS. | |||||
| 16 | 10 | SIF demand/action sequences aligned with Cause & Effect matrix and shutdown hierarchy levels. | |||||
| 17 | 10 | Cybersecurity requirements captured (zones/conduits, user roles, remote access, logging, hardening baseline). | |||||
| 18 | 10 | Device selection constraints (certification, SFF, λ values, failure modes) stated or referenced to data sources. | |||||
| 19 | 10 | Bypass duration limits, KPIs, and monitoring rules defined (notifications, SOE, management approval workflow). | |||||
| 20 | 10 | Failure modes and action on detected/undetected faults defined (degraded operation vs trip to safe state). | |||||
| 21 | 10 | Proof test success criteria, recording, and restoration requirements described (post-test resets, bypass removal). | |||||
| 22 | 10 | Documentation traceability matrix provided (HAZOP/LOPA → SRS → design → validation → O&M). | |||||
| 23 | 10 | Assumptions, enabling conditions, and external dependencies listed and justified in the SRS text/tables. | |||||
| 24 | 10 | SRS review and approval completed by Process, I&C, Operations, Safety, and Management (signatures/dates). | |||||
| 25 | 10 | Version control and archiving established; baseline issued; change control linked to MOC for future updates. |
Note: As requested, the IEC 61511 clause reference is kept the same (Clause 10 — Safety Requirements Specification) for all 25 checklist items.
Phase 4 — Design & Engineering of SIS (IEC 61511)
Verification Checklist
| # | IEC 61511 Clause | Requirement | Outcome | Verification Comments | Recommendation | By | Status |
|---|---|---|---|---|---|---|---|
| 1 | 11.2 | Verify SIS hardware/software design meets SRS and target SIL requirements. | |||||
| 2 | 11.3 | Confirm system architecture (sensors, logic solver, final elements) matches SRS (redundancy/voting). | |||||
| 3 | 11.4 | Use appropriately certified/assessed components (IEC 61508/third-party) or justify proven-in-use evidence. | |||||
| 4 | 11.5 | Validate reliability data (λ, SFF) and architectural constraints; calculate PFDavg/PFH as per SRS intervals. | |||||
| 5 | 11.6 | Logic solver selection justified (capacity, scan time, diagnostics, safety certifications, cybersecurity features). | |||||
| 6 | 11.7 | Verify segregation/independence between SIS and BPCS/F&G (power, networking, I/O, cabinets, software). | |||||
| 7 | 11.8 | Confirm wiring philosophy: dedicated safety I/O, line monitoring, shielding, earthing, and EMC compliance. | |||||
| 8 | 11.9 | Redundancy & voting logic implemented as designed (1oo2, 2oo3, etc.) with common-cause mitigation documented. | |||||
| 9 | 11.10 | Application program documented (SIF logic diagrams, narratives, variables, ranges, scaling, comments, versioning). | |||||
| 10 | 11.11 | Diagnostics/watchdogs and fault handling configured to drive safe state within Process Safety Time (PST). | |||||
| 11 | 11.12 | Fault-tolerant design validated (power redundancy, network redundancy, hot-standby where required). | |||||
| 12 | 11.13 | Provide signal simulation/test provisions and safe test methods for SIFs (no loss of protection during tests). | |||||
| 13 | 11.14 | Cybersecurity-by-design applied (access control, hardening baseline, secure comms, logging, remote access rules). | |||||
| 14 | 11.15 | Environmental protection validated (temperature, humidity, IP/NEMA, corrosive atmosphere, vibration/shock). | |||||
| 15 | 11.16 | Hardware selection compliant with SRS and manufacturer limitations; proven device lists adhered to. | |||||
| 16 | 11.17 | Instrument datasheets/specs match SRS (ranges, accuracy, response time, fail-safe direction, certification). | |||||
| 17 | 11.18 | Cause & Effect matrix and shutdown hierarchy traceable to SIF logic; interlocks comprehensively covered. | |||||
| 18 | 11.19 | Interposing relays/isolators/barriers selected and approved; failure modes and SIL impact assessed. | |||||
| 19 | 11.20 | Application software lifecycle controlled (requirements → design → code → test); version/config management applied. | |||||
| 20 | 11.21 | Panel/cabinet design drawings validated (layout, heat load, segregation, terminals, labeling, space for spares). | |||||
| 21 | 11.22 | Earthing, bonding, and shielding practices documented and consistent with EMC/safety requirements. | |||||
| 22 | 11.23 | 3rd-party/package interfaces defined and tested (signals list, protocols, fail-over, interlocks, SAT/FAT scope). | |||||
| 23 | 11.24 | Spare capacity and scalability confirmed (I/O, CPU, network, cabinet space) per project/operations needs. | |||||
| 24 | 11.25 | Formal design reviews held; actions tracked to closure; approvals recorded in document control system. | |||||
| 25 | 11.26 | As-built design documentation alignment plan defined (redlines → updates → baselining for validation/commissioning). |
Note: Clause numbers reference IEC 61511-1, Clause 11 (Design & Engineering) with typical sub-items used in practice.
Phase 5 — Installation, Commissioning & Validation (IEC 61511)
Verification Checklist
| # | IEC 61511 Clause | Requirement | Outcome | Verification Comments | Recommendation | By | Status |
|---|---|---|---|---|---|---|---|
| 1 | 12.2 | Verify installation executed per approved drawings, SRS, and vendor instructions (location, orientation, impulse lines). | |||||
| 2 | 12.3 | Confirm cable continuity, insulation resistance, and earthing tests are completed & recorded (as-found/as-left). | |||||
| 3 | 12.4 | Validate loop checks for each SIF path (sensor → logic solver → final element) against Cause & Effect matrix. | |||||
| 4 | 12.5 | Check calibration certificates traceable to national/international standards; ranges & LRV/URV per SRS. | |||||
| 5 | 12.6 | Confirm tag numbers, labelling, direction-of-fail, and fail-safe positions are correct on devices and panels. | |||||
| 6 | 12.7 | Verify safety barriers/isolators and instrument air quality installed & configured per design and area classification. | |||||
| 7 | 12.8 | Confirm logic solver loaded with approved application; checksum/version recorded; baseline stored in DC system. | |||||
| 8 | 12.9 | Validate interlocks and trips tested per approved procedures (simulation/energized tests) without compromising safety. | |||||
| 9 | 12.10 | Check all bypass/override/inhibit switches are secure, logged, timed, alarmed, and authorized as per SRS/management rules. | |||||
| 10 | 12.11 | Ensure initial proof tests executed as defined (coverage, steps, acceptance criteria) and restoration to normal documented. | |||||
| 11 | 12.12 | Verify trip sequences and shutdown levels match approved Cause & Effect and shutdown hierarchy (no omissions). | |||||
| 12 | 12.13 | Confirm de-energize/energize-to-trip philosophies implemented as designed; fail-safe confirmed on loss of power/signal. | |||||
| 13 | 12.14 | Check alarm verification in BPCS/DCS: priorities, colors, annunciation, SOE timestamps, and operator guidance text. | |||||
| 14 | 12.15 | Validate operator HMI messages, permissives, inhibits, reset, and restart logic align with the SRS and user procedures. | |||||
| 15 | 12.16 | Verify deviations/non-conformances captured with corrective actions, owners, and closure dates in the commissioning log. | |||||
| 16 | 12.17 | Confirm punch list created, prioritized, and closed before validation sign-off (or justified waivers approved). | |||||
| 17 | 12.18 | Ensure red-line markups captured on P&IDs, I/O, logic, hook-ups, and panel drawings for as-built updates. | |||||
| 18 | 12.19 | Verify test reports and certificates (site acceptance, leak tests, stroking, PST checks) are signed & filed. | |||||
| 19 | 12.20 | Confirm certification dossiers (Ex, material, calibration, factory certs) are complete, indexed, and archived. | |||||
| 20 | 12.21 | Validate final safety validation witnessed by Client/Operations; acceptance criteria met; punch list cleared or waived. | |||||
| 21 | 12.22 | Confirm sequence logic simulation (where applicable) demonstrates PST compliance and correct safe-state behavior. | |||||
| 22 | 12.23 | Check reset/restart sequences tested, including interlocks, permissives, and restoration of bypasses/inhibits. | |||||
| 23 | 12.24 | Validate issue of a comprehensive validation summary report with non-conformances and close-out evidence. | |||||
| 24 | 12.25 | Ensure commissioning completion certificates signed (e.g., MCC, subsystem handover, system acceptance forms). | |||||
| 25 | 12.26 | Verify turnover/hand-over dossier completeness (as-builts, SRS baseline, test packs, spares, O&M manuals). |
Note: Clause numbers reference IEC 61511-1, Clause 12 (Installation, Commissioning & Validation) with typical sub-items used in practice.
Phase 6 — Operation & Maintenance (IEC 61511)
Verification Checklist
| # | IEC 61511 Clause | Requirement | Outcome | Verification Comments | Recommendation | By | Status |
|---|---|---|---|---|---|---|---|
| 1 | 16 | Verify O&M manual approved and available for all SIS systems and subsystems. | |||||
| 2 | 16 | Confirm operators and maintenance staff trained and competent on SIS operation and bypass rules. | |||||
| 3 | 16 | Ensure operating procedures incorporate SIF initiation, reset, bypass, and override instructions. | |||||
| 4 | 16 | Verify preventive maintenance and proof test schedules established per SRS intervals. | |||||
| 5 | 16 | Check bypass authorization, time limits, and management approval in place per company standards. | |||||
| 6 | 16 | Ensure alarm management compliant with corporate philosophy (priority, acknowledgment, limits). | |||||
| 7 | 16 | Verify proof tests executed as planned; coverage recorded; any failures investigated & closed. | |||||
| 8 | 16 | Confirm calibration and functional test results stored in asset management or maintenance system. | |||||
| 9 | 16 | Verify spares inventory defined; critical SIS components have lead-time tracking and replacement strategy. | |||||
| 10 | 16 | Check corrective maintenance procedures exist for SIS devices, including failure reporting and investigation. | |||||
| 11 | 16 | Confirm maintenance records traceable to device ID, date, technician, and test instrument used. | |||||
| 12 | 16 | Ensure demand rate vs design rate monitored to verify risk assumptions remain valid. | |||||
| 13 | 16 | Validate SIS diagnostics monitored; failures and degraded modes alarmed to operations and maintenance. | |||||
| 14 | 16 | Ensure bypass logs and overrides reviewed daily/weekly by instrument & safety engineers. | |||||
| 15 | 16 | Verify maintenance backlog and overdue proof tests monitored; justifications recorded if delayed. | |||||
| 16 | 16 | Confirm personnel competence and authorization matrix maintained for SIS maintenance activities. | |||||
| 17 | 16 | Ensure cybersecurity controls maintained (password rotation, backup integrity, remote access management). | |||||
| 18 | 16 | Validate management of change applied for any configuration, logic, or component modification during O&M. | |||||
| 19 | 16 | Confirm event data analysis performed (near misses, false trips, demand failures) and lessons captured. | |||||
| 20 | 16 | Verify SIS documentation (SRS, C&E, logic diagrams) updated after any operational changes. | |||||
| 21 | 16 | Ensure partial stroke testing of shutdown valves performed at defined intervals and results recorded. | |||||
| 22 | 16 | Check spurious trip events analyzed for root cause and action plans implemented to reduce recurrence. | |||||
| 23 | 16 | Validate audit of SIS maintenance activities conducted periodically by independent function or QA. | |||||
| 24 | 16 | Confirm review of proof test effectiveness, coverage, and findings after each campaign or turnaround. | |||||
| 25 | 16 | Ensure periodic O&M performance review meeting held to evaluate SIS reliability and compliance trends. |
Note: Clause references follow IEC 61511-1 Clause 16 (Operation and Maintenance) with representative checklist items for typical SIS life-cycle verification.
Phase 7 — Modification (IEC 61511)
Verification Checklist
| # | IEC 61511 Clause | Requirement | Outcome | Verification Comments | Recommendation | By | Status | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 17 | Verify that a formal Management of Change (MOC) process exists and is applied for all SIS modifications. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 2 | 17 | Confirm all modifications assessed for impact on safety integrity and functional performance before implementation. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 3 | 17 | Ensure updated SRS reflects modification details, logic, hardware, and documentation revisions. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 4 | 17 | Check revised SIL verification performed to confirm modified SIF continues to meet target SIL. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 5 | 17 | Verify all modified logic and configuration changes tested (offline or simulated) prior to implementation in service. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 6 | 17 | Confirm configuration and logic backups taken before and after modification; checksums verified. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 7 | 17 | Ensure updated documentation (P&ID, logic, wiring, datasheets) issued under controlled document system. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 8 | 17 | Verify affected personnel trained and notified of the modification before return to service. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 9 | 17 | Confirm re-validation or partial functional testing performed on the modified SIF. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 10 | 17 | Check revised logic/software approved by authorized engineering and safety representatives. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 11 | 17 | Ensure bypasses or temporary jumpers used during modification are controlled, logged, and removed post-testing. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 12 | 17 | Confirm modification request, justification, and approvals documented in MOC form and linked to records. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 13 | 17 | Verify rollback/restore plan available in case of modification failure during implementation. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 14 | 17 | Ensure hazard review (HAZOP/LOPA) re-performed when modification impacts process conditions or protection layers. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 15 | 17 | Check cybersecurity risk assessment updated for the modification and any new components added. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 16 | 17 | Verify version control maintained across software, logic, and documents; obsolete revisions archived. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 17 | 17 |
Phase 8 — Decommissioning (IEC 61511)Verification Checklist — 25 Items • InstruNexus
www.instrunexus.com
Verification ChecklistTip: Click “Enable Inline Editing” to type directly into Outcome / Comments / Recommendation / By / Status cells, then print to PDF.
Note: Decommissioning is treated within the IEC 61511 lifecycle framework; use this checklist with site standards and governance for end-of-life activities. Phase 9 — Verification (IEC 61511)Verification Checklist — 25 Items • InstruNexus
www.instrunexus.com
Verification ChecklistTip: Click “Enable Inline Editing” to type directly into Outcome / Comments / Recommendation / By / Status cells, then print to PDF.
Note: All items reference IEC 61511-1 Clause 18 — Verification. Adjust wording to match your project’s corporate procedures and templates. Phase 10 — Functional Safety Assessment (FSA) (IEC 61511)Verification Checklist — 25 Items • InstruNexus
www.instrunexus.com
Verification ChecklistTip: Click “Enable Inline Editing” to type directly into Outcome / Comments / Recommendation / By / Status cells, then print to PDF.
Note: Items reference IEC 61511-1 Clause 5.2.6 — Functional Safety Assessment. Select the FSA level (1–5) appropriate to your project stage and risk. Phase 11 — Management of Functional Safety (IEC 61511)Verification Checklist — 25 Items • InstruNexus
www.instrunexus.com
Verification ChecklistTip: Click “Enable Inline Editing” to type directly into Outcome / Comments / Recommendation / By / Status cells, then print to PDF.
Note: This checklist aligns with IEC 61511-1 Clause 5 — Management of Functional Safety and provides verification points for FSM implementation and sustainability. |